How to build a WIP schedule your surety will trust

Your bonding line depends on how much your surety trusts your numbers, and the work-in-progress (WIP) schedule is where that trust is won or lost. Here is how a clean WIP schedule is built, what underwriters look for, and the mistakes that shrink bonding capacity.

Key takeaways
  • The WIP schedule ties every open job to the income statement: contract value, estimated cost, cost to date, percent complete, earned revenue and billings.
  • Most contractors use the cost-to-cost method: percent complete equals cost to date divided by estimated total cost.
  • Underbillings (costs and earnings in excess of billings) get more scrutiny than overbillings because they can hide cost overruns.
  • Sureties watch gross profit fade: estimated margins that shrink from one schedule to the next.
  • A WIP schedule updated monthly, and reconciled to the general ledger, is worth more than a perfect one prepared once a year.

What a WIP schedule is and why your surety cares

A WIP schedule lists every contract that is open at the end of a period and shows, for each one, how much revenue you have earned compared with how much you have billed. It is the bridge between your job cost system and your financial statements. For contractors that recognize revenue over time, the WIP schedule is the support for a large part of reported revenue and gross profit.

Your surety uses it to answer three questions: is the company making the margins it bids, is it billing in step with the work, and how much unfinished work (backlog) is already committed against its working capital. A schedule that answers those questions clearly makes it easier for an underwriter to support a larger single-job and aggregate bond limit. A schedule that does not reconcile, or that changes estimates without explanation, makes the underwriter cautious.

The columns that matter

A practical WIP schedule has these columns for each job:

  • Contract value, including approved change orders.
  • Estimated total cost, updated by the project manager each period.
  • Estimated gross profit, the contract value less estimated total cost.
  • Cost to date from the job cost ledger.
  • Percent complete, cost to date divided by estimated total cost.
  • Earned revenue, contract value times percent complete.
  • Billed to date from your billing records.
  • Over (under) billing, billed to date less earned revenue.
  • Cost to complete and backlog, the work and revenue still ahead.

Totals for earned revenue and cost should tie to the income statement for jobs in progress, and the total over and under billings should tie to the balance sheet. If they do not tie, fix that before anything else.

Overbillings, underbillings and what they signal

Overbillings (billings in excess of costs and earnings) mean you have billed ahead of the work. Modest overbillings are normal and often a sign of good billing discipline. They are a liability, because you owe the customer work you have already been paid for, so they also mean that some of your cash is not really yours yet.

Underbillings (costs and earnings in excess of billings) mean you have done work you have not billed. Sometimes that is timing. Often it is a sign that a job is running over budget and the estimate has not been updated, so percent complete is overstated. Underwriters look hard at large or growing underbillings and at underbillings on jobs that are nearly complete.

Free download: the WIP schedule template

A ready-to-use WIP schedule with cost-to-cost formulas, over and under billings, gross profit to date, cost to complete and backlog totals.

One email with the file. No newsletter unless you ask.

Gross profit fade and estimate discipline

Fade is the drop in a job's estimated gross profit from one WIP schedule to the next. Some fade on a hard job is expected. Fade across many jobs, or a pattern of jobs that close at lower margins than bid, tells the surety your estimates are optimistic. Gain (margin that improves) is less of a concern but can signal conservative early estimates that understate profit.

Good practice is simple: require the project manager to sign off on estimated cost to complete each month, keep a closed-job report that compares final margin with bid margin, and explain any job with fade above a threshold you set.

What goes in a bonding package

Along with the WIP schedule, sureties typically ask for year-end financial statements on a percentage-of-completion basis (reviewed or audited by a CPA firm once your program grows), interim statements, a completed-contracts schedule, an aged receivables and payables listing, bank line details, and a résumé of key people. The financial statements themselves come from your CPA firm. Our part is the schedule, the job cost cleanup and the support behind them, so your CPA's work goes faster and your surety sees consistent numbers all year.

Common mistakes that shrink bonding capacity

  • Using billings as a stand-in for percent complete.
  • Leaving estimated total cost at the original bid while actual costs climb.
  • Unapproved change orders counted in contract value.
  • Job cost that does not tie to the general ledger.
  • Preparing the schedule only at year end, so problems surface all at once.
  • Mixing equipment and overhead costs into jobs inconsistently.

Need a WIP schedule your surety will accept?

We set up the WIP schedule and job cost structure, then prepare a bonding readiness package you can hand to your agent.

WIP schedule and job cost setup $3,500 · Bonding readiness package $5,500

See the service   Get a fixed-fee quote

FAQ

What is the difference between overbilling and underbilling?

Overbilling means billings exceed earned revenue on a job; it is a liability. Underbilling means earned revenue exceeds billings; it is an asset and often a warning sign that costs are running over.

How often should a contractor update the WIP schedule?

Monthly is best. Sureties and banks often ask for it quarterly, but a monthly schedule catches fade and billing gaps while they can still be fixed.

Do you prepare reviewed or audited financial statements for bonding?

No. StrategX is a consulting firm. We build the WIP schedule, clean up job costing and prepare the support package; your CPA firm issues the reviewed or audited statements.

What percent complete method should I use?

Most contractors use cost-to-cost. Other input or output methods can fit some contracts. The method should match how the work is actually performed and be applied consistently.

StrategX Advisory is a consulting firm (a dba of Intermountain CFO Group, LLC), not a licensed CPA firm. This guide is general information, not accounting, tax, legal or investment advice, and it is not a valuation.

Grow your bonding line

A clean WIP schedule and a consistent monthly close are the fastest way to more capacity.

Get a fixed-fee quote   See our fees

Prefer to talk first? Book a 30-minute call →

Get a fixed-fee quote